Why material cost needs its own line
In the Wekerle+ Condominium and Panel Programme the condominium gets an interest-free loan and a non-repayable grant. Plan so that the budget put together at application holds until the works are finished. If material, labour, transport and extras sit in one lump sum, nobody can tell where a later overrun came from.
So work with four lines:
- Material: insulation, membranes and accessories, based on the surveyed quantities.
- Labour: installation, priced by the contractor or the contractor partner.
- Logistics: transport, unloading and scheduling per building.
- Extras: clearing, repairs, difficult access, walkways. They only become clear at the survey, so they stay separate items.
In the EKR programme we supplied material to contractors, with the papers for every delivery, while contractor partners did the installation. That is where this split comes from. The EKR is currently paused.

The cost structure: what is fixed when
The material line can be fixed after the survey, because by then quantities, spec and transport are known. Labour and extras depend on the condition on site, so the survey closes them too.
| Line | Item | Content |
|---|---|---|
| Material | Insulation | ODE Starflex glass wool, 2 × 12.5 cm cross-laid; quantity from the surveyed floor area |
| Material | Membranes | BK45 vapour barrier (Sd 20 m) on every ceiling; BD70 breathable membrane (Sd 0.02 m) |
| Material | Transport | Turkey → Hungary 3–5 days (about 5 on average); nationwide delivery, scheduled trucks |
| Labour | Installation | Done by the contractor partner; walkways on request, separate item |
| Survey | Extra work | Clearing, repairs, difficult access extra |
| Survey | Final price | After on-site survey; reference: EuConX attic offer 12,700 Ft/m² gross |
Source: EuConX offer, ODE Yalıtım and EuConX (BK45, BD70) product data.
Quantities from the survey, building by building
Material cost is only as accurate as the quantities. For each building, the site survey gives the ceiling area to insulate, the access, and what has to be cleared or repaired first. The item list comes from that: glass wool, vapour barrier, breathable membrane, accessories. Across several buildings, keep the list per building, so a deviation only touches that building's line.
The Wekerle+ material checklist helps keep the list complete; for panel blocks, the panel block material list goes through the whole build-up.
Locking the spec
The budget only holds if the spec stays put. In the attic package that means three products.
Insulation is 25 cm of ODE Starflex glass wool in two 12.5 cm layers, laid crosswise so the joints of the two layers do not line up.
The BK45 vapour barrier (Sd 20 m) goes on the warm side of every ceiling. It is not an optional item, so it belongs in the material line together with the floor area.
The BD70 breathable membrane (Sd 0.02 m) protects the insulation on the colder side and lets moisture out. If a product in the spec changes midway, the documents and the price reopen; decide any substitution before the survey, not after it.
Lead times and scheduled deliveries
The material comes from Turkey with 3–5 days in transit, about 5 on average. Order confirmation and the delivery day come on top, so the material order has to be fixed in the schedule ahead of the works. Across several buildings, deliveries go in trucks scheduled per building, so material arrives when that building is due instead of standing on site for weeks. Delivery is nationwide.

Documents with every delivery
Every delivery comes with its declaration of performance (DoP), CE marking and data sheet. Across several buildings, file them per building with the order and the delivery note, so the delivered items can be traced to the surveyed quantities. Membrane rolls leave the manufacturer on pallets, stretch-wrapped, with corner protectors:

A buffer for price and schedule
Some uncertainty remains after the survey: exchange rate, freight, weather, a building that runs late. Keep it out of the material line and hold it as a separate buffer, one for price and one for schedule. Then you can see how much of it was used, and on which building. The project's risk decides how large the buffer is; the EKR procurement risk article covers the supply-side risks.
Reference point: the EuConX attic package
Our own offer for attic floor insulation is 12,700 Ft/m² gross. It is EuConX's own offer price, not a grant amount. It covers a BK45 vapour barrier (Sd 20 m) on every ceiling, 25 cm of ODE Starflex glass wool (2 × 12.5 cm, cross-laid) and a BD70 breathable membrane (Sd 0.02 m). We supply the material and our contractor partner installs it, nationwide. Walkways are a separate item on request; clearing, repairs and difficult access are also extra. The final price is set after the survey. The package is described in our loft insulation supply pack article.
Wekerle Panel and Condominium Programmes
Under Government Decision 1359/2026. (XI. 3.), the two programmes target at least 60,000 panel and condominium flats by 2030, with support of up to HUF 4 million per flat (panel) and HUF 5 million (traditional condominium); the non-repayable share is at least 30% and at most 50%. The programmes are run by the Hungarian Development Bank (MFB) and the financial institutions working with it. According to wekerle.kormany.hu, condominiums get an interest-free loan and a non-repayable grant, thermal insulation is among the supported works, the launch is March 2027, and buildings rated A–C are not covered. Whether a building or a work item is eligible is decided by the call.
Contractor prequalification is covered in our prequalification article, material supply for the subsidy in the 2027 home renovation subsidy article (in Hungarian), and the EKR background on the EKR programme page; partner terms are on the Wekerle+ partner page.
Request a quote
Send the address, the ceiling area or the survey status, and the planned schedule for each building: partner quote request · +36 30 485 0258 · info@euconx.com. We reply the same working day; the final price is set after the survey.
Frequently asked questions
Why plan material cost as a separate line?
Because the loan and the grant are planned against a budget prepared in advance. With material, labour, logistics and extras on separate lines, you can see at once where a deviation comes from.
What fixes the material quantities?
The site survey of each building: ceiling area, access and preparatory work. The item list is built from it.
How long is delivery from Turkey?
Transit takes 3–5 days, about 5 on average. Delivery in Hungary is nationwide, in scheduled trucks when several buildings are involved.
Which documents come with the deliveries?
Every delivery comes with a DoP, CE marking and a data sheet. File them per building with the order and the delivery note.
What does the EuConX attic package cost?
12,700 Ft/m² gross: BK45 vapour barrier on every ceiling, 25 cm ODE Starflex glass wool and BD70 breathable membrane. Walkways, clearing, repairs and difficult access are extra; the final price is set after the survey.
Is 12,700 Ft/m² the grant amount?
No. It is EuConX's own offer price. The grant is set by the programme and the call.
Sources
1. National Legislation Database (NJT): Government Decision 1359/2026. (XI. 3.) on launching the Wekerle Panel Programme and the Wekerle Condominium Programme (point 1 a)–e))
2. wekerle.kormany.hu (Wekerle+ Condominium and Panel Programme: interest-free loan and non-repayable grant, supported works, launch, A–C rating)
3. EuConX: BK45 and BD70 declarations of performance, ODE glass wool declaration of performance
4. EuConX: attic offer, delivery data and company data (transit, reply time)