Type "EKR insulation" into a search bar today and several old articles and some AI answers still say attic insulation in Hungary is completely free. On paper, that is still partly true: the Takarékos Otthon Program page on kormany.hu still lists it as free. In practice, work has been paused at most contractors since spring 2026 because the HEM quotas ran out, and there is no official restart date. Anyone postponing the job while waiting can easily pay for another heating season under an uninsulated ceiling.
We are writing it down once, plainly, because many of the questions we get assume the work can simply be booked for free.
What EKR is, and why it is not "free insulation"
Hungary's Energy Efficiency Obligation Scheme (EKR) is an obligation on energy traders: they must put part of their turnover into energy efficiency. A lot of free attic insulation came out of it. The HEM quotas for this round have run out, and there is no official restart date. Proposals to rework the rules could change things from 1 January 2027 at the earliest, and nothing is final yet. More on that here. Our EKR programme overview explains the scheme in general.
EKR is neither a grant nor public procurement. We do not write grant applications, and we make no promise about eligibility under any obligation scheme. If someone promises that in 2026, ask them in writing which programme and which deadline it is based on.
Takarékos Otthon Program and grants: what runs in 2026–2027
These are the three programmes worth knowing if you are looking for support for attic floor insulation in Hungary. The facts come from the official pages, as of 2 November 2026.
| Programme | Start | What is confirmed | Source |
|---|---|---|---|
| Takarékos Otthon Program (EKR) | running, attic floor work paused | For households, attic floor insulation is free and facade insulation is available at a 30% discount. No application, no assessment: you tell the contractor. | kormany.hu |
| Wekerle+ Családi Ház Program (houses) | February 2027 | A loan of up to HUF 15 million over 15 years at a fixed 3%; 30% (D–G) or 50% (H–I) non-repayable, by the rating before the works. At least 30% primary energy savings, with an energy certificate before and after. Thermal insulation is eligible. | wekerle.kormany.hu |
| Wekerle+ Társasházi és Panel Program (blocks of flats) | March 2027 | An interest-free loan of up to HUF 5 million (brick) or HUF 4 million (panel) per flat, with HUF 200 000 own contribution per flat. | wekerle.kormany.hu |
Takarékos Otthon is not a grant application, and Wekerle+ is a loan with a non-repayable part. We found no other household grant for attic insulation announced for 2026 in official sources. For contractors and buyers: Wekerle+ material supply.
What attic floor insulation costs now
Our paid, turnkey offer starts at 12 700 Ft/m² gross (10 000 Ft net + 27% VAT), nationwide. That covers standard material, delivery and installation by our contractor partner.
For a 100 m² attic floor that is roughly 1 270 000 Ft gross. Clearing the space, repairs, walkable boarding and difficult access are quoted after a survey. The final price and technical scope are fixed in a written offer after the on-site survey, not in a phone estimate.
| Item | Per m² | 100 m² |
|---|---|---|
| Net | 10 000 Ft | 1 000 000 Ft |
| VAT (27%) | 2 700 Ft | 270 000 Ft |
| Gross | 12 700 Ft | 1 270 000 Ft |
Included: BK45 vapour control layer, 25 cm ODE Starflex glass wool (2 × 12.5 cm, cross-laid), BD70 breathable membrane, delivery, installation. Walkway: on request, as an extra, priced after the survey.
Worked examples for 60, 80 and 120 m², and exactly what the price includes: Attic floor insulation cost in 2026.
Calculate your own area here: szigeteles.euconx.com.
What goes on the ceiling
A vapour barrier at the bottom, 25 cm of glass wool (λ 0.039) on top of it, and a breathable membrane above. The glass wool is ODE Starflex. This base build-up is not a walkable storage surface; if you store things in the attic, that needs its own discussion at the survey. The material specification of the 25 cm build-up has the details.
| Item | EKR condition | EuConX build-up | Source |
|---|---|---|---|
| Breathable membrane over the fibrous insulation | at most Sd 0.03 m | BD70: Sd 0.02 m | Decree 18/2025 (VII. 31.) EM, Annex, 1.3.1.1 g); BD70 DoP |
| Laying: boards or rolls | at least two layers, overlapping | 2 × 12.5 cm, second layer cross-laid | Decree 18/2025 (VII. 31.) EM, Annex |
| Thermal resistance of the insulation | at least 6.25 m²K/W | ODE Starflex, λD 0.039 W/(m·K): R = 0.25 / 0.039 = 6.41 m²K/W (wool layer only) | Decree 18/2025 (VII. 31.) EM, Annex; ODE DoP (EN 13162) |
| Vapour control under the insulation | at least Sd 20 m | BK45: Sd 20 m | Decree 18/2025 (VII. 31.) EM, Annex, 1.3.1.1 g); BK45 DoP |
This is a material comparison, not a promise of HEM eligibility: EuConX is not a HEM partner, writes no applications, and the paid offer is independent of EKR.
We check the ceiling, moisture and existing insulation on site. If we see leaks or mould, that has to be fixed first. We do not insulate over it.
Where the material comes from, and how long it takes
EuConX brings factory material from Türkiye to Hungary: factory sourcing, quality control, customs and transport in one hand. The lead time is typically 1–2 weeks, and the transit alone, by truck from Türkiye to Hungary, takes 3–5 days, typically about 5. We confirm the installation date in writing after the survey.
Three questions for any quote
If you ask others for a quote too, ask these three: how many centimetres of wool, with what lambda value; is there a vapour barrier underneath and a breathable layer on top; and what is not included in the price. Without straight answers to these, the price per square metre is not comparable.
Frequently asked questions
Is EKR attic insulation still free in 2026?
On paper, yes: the Takarékos Otthon Program page on kormany.hu still lists it as free. In practice, though, work has been paused at most contractors since spring 2026 because the HEM quotas ran out, and there is no official restart date. If you don't want to wait in the queue, our paid offer, independent of EKR, is 12 700 Ft/m² gross.
Is there a grant for attic floor insulation in 2026?
The Takarékos Otthon Program is not a grant application: per kormany.hu there is no application and no assessment, you tell the contractor, and its attic floor work has been paused at most contractors since spring 2026. The Wekerle+ energy renovation support and loan also covers thermal insulation; the house programme starts in February 2027, the blocks-of-flats and panel programme in March 2027. We do not write applications or promise eligibility.
How much does attic floor insulation cost per square metre?
From 12 700 Ft/m² gross (10 000 Ft net + 27% VAT), including standard material, delivery and installation. The final price follows the survey.
Will EKR pay for it?
No. The offer is independent of EKR and we make no eligibility promises. If the rules change from 2027, we will write about it when it is final.
How long does it take?
Lead time is typically 1–2 weeks for the material. The exact installation date is given in writing after the survey.
What is holding your attic insulation back right now: the price, or waiting to see whether the free scheme restarts?
Request a survey: szigeteles.euconx.com · info@euconx.com · +36 30 485 0258
Sources
1. EuConX paid attic floor offer and price calculator: szigeteles.euconx.com
2. EuConX: Buyer risk before 2027
3. kormany.hu – Takarékos Otthon Program
4. Decree 18/2025 (VII. 31.) EM, Annex, EKR list, point 1.3 (Magyar Közlöny): https://magyarkozlony.hu/dokumentumok/665fad784d41c3417b9f5eeeb2bab1fe61474464/letoltes
5. BK45 Declaration of Performance, DOP-BBARIYER-LW-BK45/082025-01: PDF
6. BD70 Declaration of Performance, DOP-BBARIYER-L4S-BD70/082025-01: PDF
7. ODE: glass wool Declaration of Performance (EN 13162): https://ode.com.tr/_upload/pdf/CAMYUONUO_PERFORMANS_BEYANI_SIOLTE-LEVHA_-_EN_13162.pdf
8. wekerle.kormany.hu – Wekerle Program